Beginning Monday, June 15, demolition activities will commence at approximately 7:00 a.m. and continue during regular construction hours through 4:00 p.m. each workday. The project is currently scheduled for completion by mid-August, subject to weather and other unforeseen conditions.
The initial phase of work will begin in the northeast corner of the site adjacent to the Bridges Auditorium loading dock and will progress according to the planned demolition sequence outlined below.
Project Timeline Highlights
| Area | Soft Demo | Hard Demo | Foundation Demo |
|---|---|---|---|
| Wing A | June 15 – June 19 | June 22 – July 1 | July 6 – July 10 |
| Wing B (West) | June 22 – June 26 | July 2 – July 13 | July 14 – July 21 |
| Residence Area | June 29 | June 30 | July 1 – July 2 |
| Wing C | July 6 – July 10 | July 14 – July 23 | July 22 – July 28 |
| Wing B (East) | July 24 – July 25 | July 27 – July 29 | July 30 – August 10 |
*Remaining Tree Demo: June 29 – July 1
What to Expect
Throughout the demolition process, members of the campus community may notice:
- Increased construction vehicle traffic in the vicinity of Oldenborg Hall.
- Elevated noise levels associated with demolition activities.
- Occasional vibrations typical of large-scale demolition operations.
The College and its contractors are committed to conducting this work safely and responsibly. Measures will be in place throughout the project to minimize impacts on surrounding areas, including:
- Secure construction fencing around the work zone.
- Debris containment systems to ensure materials remain within the project site.
- Dust-control and environmental mitigation measures.
- Ongoing monitoring to maintain safety and regulatory compliance.
We appreciate your patience and cooperation as we complete this important phase of campus renewal. Every effort will be made to minimize disruption while ensuring the project proceeds safely and efficiently.
If you have any questions or concerns regarding the demolition activities, please feel free to contact me directly.
Thank you for your continued support and understanding.